The FIDIC 2017 edition had made significant expansion of the programme (project schedule) requirements that is part of clause 8, the primary clause which deals with time or “Commencement, Delays and Suspension”. The new changes not only mandate the software to be used but also sets out that the contract schedule must include all (logically linked) activities, and set out the sequence and timing of inspections and tests. In addition, all key dates must be identified, and all activities and milestones are to be logically linked, also identifying float, rest days and holidays as well as the delivery of materials. A supporting method statement is also a requirement.

PMWeb 7 Activities

Using a Project Management Information System (PMIS) like PMWeb and a planning software like Oracle Primavera P6 or MS Project, can help all those entities involved in delivering projects under FIDIC contract to fully comply as well as take advantages of the new schedule clauses. To start with, project owners must now expand the project schedule specifications to detail the requirements for having an integrated project schedule using the critical path method (CPM) technique.

PMWeb 7 Construction Progress Schedule

Having those detailed specifications will enable the contractors to develop the project schedule work breakdown structure (WBS) levels and resource loaded activities in accordance with the project’s requirements. To ensure compliance with sub-clause 1.1.67 the Engineer needs to have a detailed checklist to formalize the review, analysis and approval the project’s schedule. FIDIC sub-clause 1.1.67 defines the Schedule as meaning the detailed time schedule prepared and submitted by the Contractor to which the Engineer has given, or is deemed to have given, a Notice of No-Objection. The checklist can be used for reviewing, analyzing and approving baseline schedule, weekly or monthly updates, as well as the revised schedules. Using PMWeb custom form builder, a form Schedule Review and Analysis form will be created which a predefined list of all items that need to be reviewed and analyzed before a project schedule is formally approved. The form will include different tables for which different project team members can be assigned to review and analyze. Those tables will be aligned with the workflow assigned to the schedule review form to ensure formal and governed review, analysis and approval process. A PDF version of the contractor’s project schedule and other relevant reports will be attached to the schedule review form.

PMWeb 7 Scheduling Forms Schedule Review

The new FIDIC revisions also emphasize on how the project schedule can be used to manage all project activities including but not limited to mobilization, site access (sub-clause 8.3(i)), technical submittals review and approvals, procurement, permits and no-objection certificates, owner’s activities, construction activities, interface activities with other contractors, testing and commissioning, handover and other on-site and off-site activities. Since most of those processes will be managed in a PMIS like PMWeb, it is critical that both PMWeb and the tool used to create the project schedule, whether it was Oracle Primavera P6 or MS Project schedule are aligned. PMWeb scheduling module allows importing the activities schedule information included in those schedules including the baseline, periodical updates and revised versions.

PMWeb 7 Scheduling Schedule Link Schedule

Accordingly, for the submittal log that the contractor needs to submit along with the project’s baseline schedule, each submittal item must specify the project schedule activity that relates to each submittal item. This will immediately provide the planned submit, review and approval dates for this submittal item. PMWeb submittal items module allows having this feature as well as it allows importing the complete submittal log along with the linked schedule activities from MS Excel.

PMWeb 7 Engineering Forms Submittals Items

The modified FIDIC edition also places an obligation on the Contractor to update the project schedule to reflect actual progress. FIDIC clause 4.21 (Progress Reports) obliges the Contractor to submit a ‘comparison of actual and planned progress’ as part of the progress report. To ensure the correctness the actual progress information, the daily progress report submitted by the contractor should detail all activities that have either started, progressed or completed on that date. The report will also link the actual deployed resources, labor and non-labor, with their relevant project schedule activity. PMWeb daily report module allows capturing this information and assigning the relevant project schedule activity for each resource listed in the daily report. The daily report allows capturing the worked hours, type of work performed among others which will be needed for updating the project schedule.

PMWeb 7 Engineering Forms Daily Reports

Further, the new FIDIC edition includes a number of clauses that promote the importance of dispute avoidance by keeping the project team members aware of the review and approval actions that could have an impact on the project schedule if they are delayed. For example, in the request for information form, it is highly recommended to link the RFI to the project schedule activity that could be impacted if the RFI is not closed prior to the activity scheduled start date.

PMWeb 7 Engineering Forms RFIs

Another time-sensitive project communication document is the meeting minutes for which regardless of the purpose of the meeting, there will be actions assigned to the different project team members who must close before the agreed due date. Similar to the RFI, each meeting business item should be linked to the relevant project schedule activity. This will immediately provide the project team members with an advanced warning on the impact that delayed actions could cause to the project.

PMWeb 7 Engineering Forms Meeting Minutes

In addition, the 2017 Red Book introduces advance warning provisions (sub-clause 8.4), which require each Party to advise the other “in advance of any known or probable future events which may (a) adversely affect the work of the Contractor’s Personnel; (b) adversely affect the performance of the Works when completed; (c) increase the Contract Price; and/or (d) delay the execution of the Works or a Section (if any).” PMWeb custom form builder will be used to create the early notification form capturing in addition to the details of the event, the project schedule activity that could be impacted by this event.

PMWeb 7 Asset Managment Forms Early Warning Notice (EWN)

Although the second edition of the FIDIC form has not set a mechanism for assessing requests for extension of time (EOT), nevertheless, it is highly recommended to have a process to encourage contractors to submit their EOTs with all details to enable the Engineer to make a fair and reasonable determination in accordance with the terms of the contract and taking due regard of all relevant circumstances (FIDIC clause 3.7). The Extension of Time (EOT) request form will be used by the Contractor to demonstrate his entitlement for the time extension. PMWeb custom form builder will be used to create the form for capturing all EOT requests which include all needed fields and documents for the Engineer to review and make a decision to either approve or reject.

PMWeb 7 Asset Managment Forms (EOT) Request

Although the second edition of the FIDIC form has not set a mechanism for assessing requests for extension of time (EOT), nevertheless, it is highly recommended to have a process to encourage contractors to submit their EOTs with all details to enable the Engineer to make a fair and reasonable determination in accordance with the terms of the contract and taking due regard of all relevant circumstances (FIDIC clause 3.7). The Extension of Time (EOT) request form will be used by the Contractor to demonstrate his entitlement for the time extension. PMWeb custom form builder will be used to create the form for capturing all EOT requests which include all needed fields and documents for the Engineer to review and make a decision to either approve or reject.

PMWeb 7 Asset Managment Forms Time Impact Analysis (TIA) Report

The new FIDIC 2017 also added the requirement for supplemental provisions if the contract will provide entitlement for payments against completed milestones which could be part of the contract. When a milestone is completed, it will trigger an entitlement to payment. All such milestones should be clearly described by the Employer and the Contractor shall include all those milestones in the project schedule. PMWeb progress invoice module allows linking each payment milestone with the relevant project schedule milestone activity to automatically capture the percent complete progress for each milestone from the updated project schedule.

PMWeb 7 Cost Managment Invoices Progress Invoices

The FIDIC new edition also added the precondition for the Contractor to submit the monthly progress reports (sub-clause 4.20 (h)) which should include a comparison of planned and actual progress (sub-clause 14.3). By importing the updated project schedule into PMWeb scheduling module, a report can be designed in the desired form and format to provide this schedule comparison requirement.

PMWeb 7 Scheduling Schedule Reports Review

In conclusion, the FIDIC 2017 new edition had made significant expansion to the project schedule requirements for which the project management team and in particular the planning engineers will need to use a Project Management Information System (PMIS) like PMWeb in addition to their planning software to fulfill those additional contract requirements as well as take advantages of integrating the project schedule with the everyday processes needed to manage the project and to help avoid disputes.