For the first time, the FIDIC 2017 Red Book introduces advance warning provisions (sub-clause 8.4), which require each Party to advise the other “in advance of any known or probable future events which may (a) adversely affect the work of the Contractor’s Personnel; (b) adversely affect the performance of the Works when completed; (c) increase the Contract Price; and/or (d) delay the execution of the Works or a Section (if any).” There is no time limit for giving an advance warning, nor is there any explicit sanction for failing to do so.

This clause is similar to the “Early Warning” clause 16.1 in the NEC3 contract, often referred to as ‘the jewel in the NEC crown’, early warnings are designed to help you deliver the project on time and on budget – undoubtedly the most important KPI’s for any Project Manager! Unlike the FIDIC sub-clause 8.4, the NEC contract contains sanctions for non-compliance with the early warning process.

Using Project Management Information Systems (PMIS) like PMWeb can be used to formalize the process for managing Early Warning Notifications (EWN) or Advance Warning (AW). PMWeb custom form builder will be used to create EWN form for which it will include the needed fields for the form. Those will include Description of Early Warning, details if the Early Warning likely to (a) adversely affect the work of the Contractor’s Personnel; (b) adversely affect the performance of the Works when completed; (c) increase the Contract Price; and/or (d) delay the execution of the Works or a Section (detail the work will be affected), and advise if an Early Warning Meeting is Required. The form will also include a field the name of the project entity the EWN is issued to.

PMWeb 7 Asset Managment Forms Early Warning Notice

The attachment tab will be used to attach documents and link PMWeb records like Request for Information and other records that could be relevant to the issued Early Warning Notification. This will provide the recipient better understanding of the reported EWN.

PMWeb 7 Asset Managment Forms Early Warning Notice Link Records

PMWeb meeting minutes module will be used to document all discussions held during the weekly Early Warning Notifications meeting. During this meeting, all reported EWNs that were identified to as an “Early Warning Meeting is Required” will be discussed by the project team member. Early Warning Meeting will help all those attending the meeting to cooperate to make and consider proposals to avoid or reduce the impact of EWN, seek solutions and decide how to proceed.

PMWeb 7 Engineerings Forms Meeting Minutes

The Early Warning Notifications report will maintain an active register of all submitted EWNs along with their details and status. The report will include visuals to highlight those EWNs that could have an impact on the project.

PMWeb 7 Early Warning Notification (EWN) Register