Having a trustworthy single version of the truth of the financial status of either an expansion or remodeling project for a retail brand is of great importance and a must requirement to the project owner. The presentation of such financial reports can be in different forms and formats. For example, the earned value management (EVM) method can be used to report each project or program financial performance as it provides a better understanding and visualization of the actual financial performance to date and what will be the impact of this performance on the forecast cost at completion and whether the project will go over budget or not.

Earned Value Management (EVM) reporting requires having the approved budget for each awarded contract or project also known as Budget at Completion (BAC), the planned spending for the approved budget or Planned Value (PV), the value of earned physical progress as reported in the project schedule or Earned Value (EV) and the Actual Cost (AC) incurred in completing the scope of work which was reported as complete. The Estimate to Complete (ETC) to complete the remaining scope of work will include in addition to the remaining contracts amount yet to be invoiced, the additional cost of potential and pending changes. The sum of the Actual Cost (AC) and Estimate to Complete (ETC) will be the Estimate at Completion (EAC) measure which is subtracted from the Budget at Completion (BAC) value, the Variance at Completion (VAC) value will be determined. The performance measures of Schedule Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI), and Cost Performance Index (CPI) will be calculated using the Planned Value (PV), Earned Value (EV), and Actual Cost (AC) measures.

PMWeb 7 EvM Performance Report by Contract

For expansion and remodeling projects that had been approved for execution, the approved cost estimate will be the starting point. The initial concept cost estimate will be further detailed to reflect the additional information that had become available to the project team as the project’s design gets further developed into drawings, specifications, and bill of quantities. The approved cost estimate will be the basis for generating the project baseline budget which will be updated as the cost estimates keep developing. The budget level of detail will be summarized at the cost breakdown structure (CBS) used in the cost estimate. Nevertheless, at all times there will be only one baseline budget and all previous versions need to be withdrawn. The project budget, which again can be in multi=-currency will be used to establish the projected budget spending plan.

PMWeb 7 Costs Budgets Budgets Construction Budget 
Main
Budget Projection

When a budget is considered to be the frozen baseline budget, any omissions, additions, or transfers within a budget, will be managed using the PMWeb budget request module. This will help keep track of all those changes, initiated by who and who has reviewed and/or approved it. Those actions will be captured from the workflow assigned to the budget request

PMWeb 7 Costs Budgets Budget Requests Original Budget Omissions 
Main

The approved cost estimate will also become the basis for generating the procurement bid packages for each project. The bid package will detail the bill of quantity line items associated with the outsourced scope of work. The procurement bid package will also be appended with the names of the bidders who are qualified to bid on the package’s scope of work. Those bidders will be selected from the PMWeb companies’ directory and for which their status will be shown as qualified.

PMWeb 7 Plans Procurement Bids Packages Electrical 
Main

From within each bid package, the entity can send Invitation to Bid emails to the selected bidders for which each invitation email will the URL link to the online bid. The online bid form can be configured to enable the bidder to submit the technical documents that are required to evaluate the bid proposal. The procurement bid package enables comparing the received bids with the approved cost estimate and award the commitment contract.

PMWeb 7 Plans Procurement Online Bids 
Main

Each awarded commitment contract or purchase order will include the contract payment terms as well as adjustments for work in place and material on-site retention and taxes. The awarded commitment contract can be a lump sum contract or remeasured plus the option to allow overbilling or not.

PMWeb 7 Costs Contract Commitments GMP Contract 
Main

As the execution of each commitment contract commences, there is a requirement to keep a very close eye on all potential changes that could impact the final cost of the awarded contract. PMWeb potential changes module provides an early warning notification of all such changes. All those potential changes that have merit will be generated as change orders while others will be disregarded or they might become a potential for claims by the contractor or supplier.

PMWeb 7 Costs Change Management Online Change Requests Differing Site Conditions

Change orders are the business process that will be used to manage all adjustments to the formally awarded commitment contract or purchase orders. Change orders could be issued for additional scope of work requested from the project owner side or identified by the contractors or suppliers. Change orders’ status can be approved, pending approval, rejected, and disputed.

PMWeb 7 Costs Change Management Commitment Office Modification
Main

As the work progresses, contractors and suppliers will raise interim payment certificates for approved work on-site or delivered materials. When the interim payment certificate is reviewed and approved, the project owner will make payment for the invoiced amount which can be in full or part of.

PMWeb 7 Costs Invoices Progresses Invoices Progress Invoice 
Main

For actual expenses incurred that are not related to an awarded commitment contract or miscellaneous invoice, PMWeb miscellaneous invoices module will be used to capture those expenses. Examples of those expenses could be permit fees, use of temporary facilities, utility usage, and other ad-hoc charges.

PMWeb 7 Costs Invoices Miscellaneous Invoices Land Purchase and Fees
Main

For the entity managing, the expansion and re-modeling projects might require adding the cost of their own team involved in managing those projects. Although in many cases this will be one of the commitment contracts for project management services, nevertheless, PMWeb timesheet module can be used to capture the spent hours of those resources for which they will be charged against the project using the pay types of whether those were regular working hours, overtime hours, weekend hours, holiday hours among others.

PMWeb 7 Tools Timesheets 
Main

PMWeb will capture all of this cost data in what is known as the cost ledger. This ledger will become the basis for creating an unlimited number of cost worksheets to organize, summarize, group, and filter the cost data in any desired format. Cost worksheets can be easily by selecting what data columns to be displayed as well as have the option to create new alias data fields by adding mathematical formulas to the captured cost data.

PMWeb 7 Costs Budgets Cost Worksheets

The data captured in all of those financial business processes will become available to be reported on in any desired form or format. Again, using some of PMWeb out-of-the-box reports, a cost worksheet is available to provide an overall integrated financial status of the project. The report can be designed to group and summarize the financial status of all projects that belong to each specific brand. The report can also be designed to have the option to drill down to a more detailed level for a project all the way until reaching the financial transaction that was the basis for the reported value.

PMWeb 7 Budget Multiple Projects(Pend & App)

Another important out-of-the-box report that comes ready with PMWeb would be the report that provides an overall status of all awarded contracts within each project that is part of a specific brand. For each contract, it will show original contract value, approved variations, revised contract value, potential and pending changes, projected at completion contract value, invoiced, and paid to date. The report will provide a list of approved change orders as well as a list of approved progress invoices.

PMWeb 7 Commitment Log by Project

Similar to the many other reports available in PMWeb, the reader can drill down to the record that has caused the reported information. For example, those could be the change order, interim payment certificates, or any other financial transaction. The output can be designed to list all record attachments and the workflow tasks status. 

PMWeb 7 Progress Invoice Form Payment 
Continuation Sheet

Tony

The world’s top organizations are selecting PMWeb because of its comprehensive features, functionality, and ease of use. Since 2007, PMWeb has been used by tens of thousands of users to manage their Plan | Build | Operate lifecycles.