For many organizations who are in particular involved in delivering engineering and construction projects, find that their projects tend to remind them of the Blind Men and the Elephant Story. It is very common to find that within each project, there are groups that will focus on capturing, analyzing, monitoring and evaluating the processes that relate to their own assigned roles and responsibilities but with very little and even no coordination with other project groups who are responsible to cover other project management processes. Thus, none of those groups as well as the project manager and other executive stakeholders can have the complete 360-degree single version of the truth on how the project is performing.

PMWeb 7 Elephant Story

Each one of those project groups will usually create the dashboard and reports that can best provide them with details of their processes’ performance and status. Those could include dashboards to report the project’s schedule performance, budget and cost, procured contracts, quality and site inspection, document management, health and safety, risk and issues among others. Each dashboard would usually include key performance indicators, other performance and trend measures as well as summary logs of key actions that need to be performed.

PMWeb 7 Cost Dashboard

There will be another project group, maybe the project control group, that will then consolidate the information from those different spreadsheets or applications used to produce the monthly project performance report. The team can use the same MS XLS file used to consolidate this multi-data sources or any other data visualization tools like MS Power BI, Tableau, Qlik among others to generate the monthly project dashboard in the desired form and format.

PMWeb 7 Project Dashboard

Nevertheless, the issue goes far beyond the wasted effort in consolidating, reviewing, analyzing and reporting the information from the different data silos and the delay in sharing this information which could make it of no or little value when it comes to making informative decisions. The real issue is that many transactions for the different processes managed by each group are interrelated with the processes managed by other groups. The links between those transactions must be clearly identified and managed if the organization is serious about having a single version of the truth when it comes to managing, monitoring and evaluating their projects’ performance.

Differing Site Conditions

To explain the seriousness of this issue, we will use the “Differing Site Conditions” event which will always have the likelihood to occur on every engineering and construction project. We will also use PMWeb project management information system to explain how can technology available today can address and support the resolution of such issue.

The risk of encountering differing site conditions should be always part of every project risk register. The likelihood and impact of this risk varies depending on the project particulars and set objectives. The most common response action for this type of risk is to escalate as we cannot avoid the cause, transfer to a third party, effectively mitigate its impact or simply accept the additional cost and delays associated with the event.

PMWeb 7 Differing Site Conditions

To ensure that all the particulars of the differing site condition are captured when it occurs and the right project team members that needs to be involved in managing this risk is escalated to, a risk occurrence template is created. Those are pre-defined templates for the top 39 risk incidents that could occur during the delivery of engineering and construction projects. The template “Occurrence Report: Differing Site Condition” has specific data fields and actions that must be performed as soon as such risk event occurs. Pictures and other supportive documents will be attached to the form as well as it will be linked to the risk form that was originally used to capture and analyze the differing site conditions risk. The form will have a workflow that will map the steps to submit, review and decide on the actions to be taken to protect the interest of the organization.

PMWeb 7 Occurence Report

Based on the particulars of the differing site condition captured in the form, the contractor’s contract administrator will issue a letter to the project owner or the authorized representative to formally notify them of this incident. The contractor would usually have pre-defined letter templates for every possible formal notification needed during the project delivery. Those are letter templates that are drafted by the organization’s legal team taken into consideration the terms and conditions of the contract agreement. The notification letter could have pictures and other supportive documents captured in the occurrence report attached to the letter as well as the link to the occurrence report.

PMWeb 7 Engineering Forms Correspondence Template Manager

The project owner and his/her authorized representative would require the contractor to submit his formal change order request that will be reviewed and assessed by them. PMWeb potential change order module will be used to submit this change request as well as any other changes that the contractor feels that there is an entitlement for additional cost and/or extension of time.

PMWeb 7 Cost Managment Change Managment Online Change Requests Details

The contractor will be required to quantify the change request as usually the associated cost with differing site conditions are not readily available in the bill of quantity. Therefore, the best source for quantifying those damages is to review the resources, labor and non-labor, that were either became idle or used to rectify the situation. The daily report is the best formal communication that details what has happened, resources consumed and project schedule activities impacted.

PMWeb 7 Engineering Forms Daily Reports Timesheet

To assess the time impact of the differing site condition incident, the contractor will use all of the information captured in the occurrence report, daily reports and updated project schedule to run the analysis. The details of this analysis will be captured in the Delay Analysis form created using PMWeb form builder. The form will be linked to all other relevant communications as well as the Time Impact Analysis (TIA) and other project schedule details will be attached to the form.

PMWeb 7 Assets Managment Forms Time Impact Analysis (TIA) Report Details

All clarifications and change order negotiation meetings will be captured in PMWeb meeting minutes module to maintain track of all events and actions taken to settle the change order. The meeting minute module is also used to capture the many project related meetings including but not limited to project kick off, safety, submittal review, progress review, interface management, handover among others.

PMWeb 7 Engineering Forms Meeting Minutes Details

When all is done and approved by the project owner, the contractor will receive the formal change order from the project owner for the differing site conditions incident. The change order will detail the financial adjustment to the contract amount along with the approved days for the delay impact.

PMWeb 7 Cost Managment Change Managment Commitment CO Details

Not only all the above processes were managed on one single platform, that is PMWeb, but the link between those interrelated processes are all captured and documented. The authorized PMWeb user can trace the records and documents that were part of any project communication captured in PMWeb. This even more important when there is a project incident or event that was not successfully identified as an incident that could impact the project cost and/or schedule. The search command allows the PMWeb user to search and locate all those records using key words that relate to the incident. Those records can be saved in an issue file where the PMWeb user can review the selected records and trace the other project communications that were linked to those selected records.

PMWeb 7 Portfolio Search Search 
Issue

In other words, the organization will not only have all the dashboards that they need to share available at all times without wasting the effort in capturing, analyzing, preparing and reporting the information, but they can drilldown to the data source to identify the project communication and all related records and documents behind what was reported.

PMWeb 7 Project Dashboard

So, if you still feel that your project reminds you of the “Blind Men and the Elephant Story” and if you strongly believe that visualizing a “Single Version of the Truth” of all project management processes across a project or all projects is a must, then you have no choice but to adopt digital transformation for your project management processes.