One of the key challenges facing Municipalities, Public Works Departments and other public sector entities who are involved in delivering capital construction projects is managing the short-term allocation of available funds across their projects’ portfolio. Those are projects that were already approved and have approved budgets for which required funds were allocated and accordingly commitment contracts were awarded. Nevertheless, governments that were negatively affected by low oil prices, COVID-19, and other challenges are now faced with constraints on providing the originally promised funds for those projects. Therefore, public sector entities are now required to slow down the delivery of some of their projects, suspend and terminate others to prioritize the allocation of short-term funds available to fund on-going projects. It should be noted that what is being done here is not project descoping that needs to be managed using budget adjustments and transfers but rather slowing down the release of approved funds for already awarded commitment contacts for construction, site supervision, PMC, etc.

Although setting the priorities for which projects to receive fund allocation and the amount of the fund to be provided depends on a number of factors that differ from one entity to another, nevertheless all those entities share one common requirement and that is how to enforce transparency in documenting the allocated short-term funds for the on-going projects.

Using a Project Management Information System (PMIS) specifically designed for managing the delivery of capital construction projects and programs like PMWeb, allows cost management processes needed for the fund allocation across on-going projects to be readily available out of the box. Mainly, there is a need to use the commitment and funding authorizations modules of PMWeb. 

To start with, using PMWeb commitment module, each project manager needs to establish the expected spending projection for the next three or six months for each awarded commmitment contract. The project manager needs to determine what the minimum spending allocation is to protect the contractual obligations of the Employer, or the public sector entity. PMWeb commitment module, and similar to the budget module, allows creating a spending projection for each commitment line item to provide what is known as the anticipated cost for each commitment contract. This anticipated spending need to be reviewed and agreed by the relevant Contractor to mitigate any contractual implications that could result from slowing down the already awarded contact’s execution should this be a requirement. 

PMWeb 7 Costs Contracts Commitments Projection for tracking Allocated Short-Term Funds

The amount of anticipated cost defined for each contract within each project becomes reported on so it can be reviewed and approved. Using one of PMWeb 150 plus out-of-the-box forms and reports, the “Committed Cost Per Month” report provides the details of the originally approved baseline budget, awarded contract value and the anticipated cost projection by month. By default, the report details the information by cost account level or cost breakdown structure for the selected fiscal year. The report can be modified to summarize this information across the complete projects portfolio with the option to drilldown to each project detailed breakdown level. This requires adding the project name field to the report. In addition the financial reporting period can be configured to 3 or 6 months window.

PMWeb Committed Cost Per Month to track Short-Term Funds

The “Commotment Cost Per Month” report can be also exported to MS Excel with all pre-defined hyperlinks to PMWeb. This is a very important function of PMWeb as the exported data can be subjected to further “What-If” analysis scenario before it is approved. In addition, this provides the project team with the ability to consume this data to create visual reporting using MS Excel or MS Power BI. It should be noted that any changes to the anticipated cost projection in MS Excel should be modified in PMWeb to ensure data consistency.

PMWeb Committed Cost Per Month to track Short-Term Funds

After approving the anticipated cost projection for each contract, the next step will be to allocate the providing funding for each line item in the commitment contract in accordance with the requested and approved fund. When the funding field is clicked at each commitment line item, the funding selector screen will popout. This screen will detail all funding sources including authorized funds available to the public entity to fund its on-going projects. Those funds could be funds available for all projects also known as portfolio, to a program of projects like education, landscaping among others and funding that is specific to a single project. 

PMWeb 7 Costs Contracts Commitments Funding Selector for tracking Short-Term Funds

All fund sources that are available for the public entity including the funds that had been authorized for a portfolio of projects, program of projects or specifci projects wll be captured in PMWeb Fund sources module. The PMweb Funding Authorizations module will be used to capture the details of all those funds that had been formally authorized to be spent on the on-going projects. The form will capture the details of funding amount, funding authorization code and other needed details to keep track of what was authorized to spend.

PMWeb 7 Costs Funding Funding Authorization

Similar to all other project management processes managed in PMWeb, supportive documents can be either attached directly to the process or uploaded into PMWeb document management repository and then attached to the relevant process transaction. The latter is the recommended approach. In addition, links to other PMWeb records as well as imported MS Outlook emails can be added to each process. 

PMWeb 7 Costs Change Managment RFC ( Online Change Request )

The above proposed solution provides public sector entities such as municipalities, public work departments among others with a quick yet proven, auditable, traceable and single version solution for managing, monitoring and evaluating the allocation of short-term funds to on-going projects. The solution that can be easily configured to produce all needed output forms and reports that will respect the Employer reporting and branding requirements. A solution that is readily available and does not need the massive cost and time to reinvent the wheel. Finally, a solution that adheres to the best practices of lean construction management for eliminating wasted effort.