One of the common line items of every single capital construction project’s bill of quantity or schedule of values is preliminaries. Those are the cost of operating the construction project and would typically include the cost of 

  • Site staff, including the project manager, engineers, foremen, quantity surveyors, office manager, storekeeper, clerks, secretarial
  • Head office staff allocated to the project, for example, designers; health and safety; company cars
  • Site offices, mess huts, toilets, running costs
  • Transport for construction equipment
  • General site labor; Services connections and running costs
  • Haul roads
  • Temporary fencing
  • Construction equipment purchases including personnel carriers, land rovers, compressors, pumps, cranes, miscellaneous
  • Scaffolding and hoists
  • Access for subcontractors
  • Small tools
  • Plant consumables including fuel and fuel distribution
  • Contract works insurances
  • Setting up compounds
  • Security
  • Signboards
  • Road-cleaning facilities 
  • Computing equipment
  • Office stationery, etc. 

(Construction Cost Management Learning from Case Studies, Keith Potts, Page 84).

Not only having an accurate estimate of all those expenses is important but it also can prove to be of great value when extension of time claims where those preliminaries items are the basis for calculating the site overheads component within each prolongation claim. In addition, it is also important to capture and document the actual expenses incurred against those preliminaries to confirm their accuracy and validity. Further, all changes to the original preliminaries estimate that could be due to claims or potential changes as well as change orders need also to be captured and well documented.

This information enables the contractor to report on the planned preliminaries cost allowance, planned preliminaries expenses allocated to work in place or Earned Value, actual preliminaries incurred to date or Actual Cost, the Estimated to Complete (ETC) cost of preliminaries which are adjusted by the performance efficiency of what was planned to be spent and actual spent being the Cost Performance Index (CPI) and how this can affect the anticipated preliminaries cost or Variance at Completion (VAC).

PMWeb 7 Capital Construction Preliminaries Status Report

Using a project management information system (PMIS) like PMWeb, this can be easily achieved. To start with, a separate estimate template needs to be created for preliminaries. This ensures that the list of possible preliminaries expenses is comprehensive, detailed to the desired control level and common to all projects that the contractor is delivering. 

For preliminaries, it is highly recommended to standardize the unit of measure for the cost estimate line items for which it will be WORK DAY. Accordingly, the quantity field will be used to reflect the project’s duration in work days. The reason for this standardized unit of measure is to ease using those rates for all claims that have prolongation cost. 

In addition, it is also recommended to assign the project schedule duration associated with each estimate line item although usually most of the preliminaries’ expenses are all associated with the summary task for the overall project duration. Of course, the contractor might elect to create different versions for the preliminary estimate template that could be best suited for projects that could differ by type, location, size, etc. 

The cost breakdown structure (CBS) levels that the contractor uses for the different cost management business processes has preliminaries as one of the cost account groups for which it is further detailed to match the preliminaries’ types and categories. Those cost breakdown structure (CBS) levels are incorporated in the project cost estimate.

PMWeb 7 Costs Budgets Cost Codes 
Main

In addition, PMWeb allows capturing the different revisions of the preliminaries cost estimate for which the final version needs to be in line with the awarded construction contract. A workflow is assigned to the estimate module to ensure that the final version of the preliminaries estimate had been formally reviewed and approved. The review and approval workflow tasks incorporates the pre-defined approval authority levels as documented in the Delegation of Authority (DOA) matrix.

PMWeb 7 Workflows Business Processes (BPM)

In addition, all supportive documents that we used to develop the estimate for preliminaries are attached to the estimate template. This also includes links to other PMWeb records as well as emails imported to PMWeb. The preliminaries estimate could also include the URL links to websites used to finalize this estimate.

PMWeb 7 Portfolio Records Projects Boston Medical Center 
Attachments

The approved preliminary cost estimate is used to generate two others important PMWeb records. The first is the budget request or adjustment to the baseline budget. The user can select to post those revisions as original budget or revised budget. This ensures that the costs associated with preliminaries are part of the project’s overall baseline budget. 

PMWeb 7 Costs Budgets Budget Requests A Substructure Scope Detail 
Main

The second PMWeb record generated from the approved preliminaries cost estimate is the commitment record. The commitment record represents the amount committed by organization for the cost of preliminaries. On monthly basis, the project team needs to quantify the actual cost incurred against those preliminaries line items. This becomes the basis for reporting the actual cost incurred against preliminaries and estimate or balance to complete each item.

PMWeb 7 Costs Invoices Progress Invoices Estimation 
Main

PMWeb potential change order module captures any potential changes identified that could impact what was originally estimated for preliminaries. The reported potential changes are subject for detailed review in accordance with the workflow assigned to this business process. 

If a potential change is approved, then it becomes the basis for generating the change order to adjust the estimated commitment for preliminaries. Those changes to the preliminaries need to be aligned with the relevant change order submitted by the contractor to the project owner regardless of if those change orders were approved, pending approval, disputed or even withdrawn.

PMWeb 7 Costs Change Managment Commitment COS 
Main

Whenever there is an approved change to the preliminaries cost estimate, the project’s baseline budget needs to also be revised by issuing a budget request. To ensure that all changes to the preliminaries’ commitment have the required budget adjustment record, PMWeb change event module is used to combine the approved budget with the approved change or changes to the preliminaries’ commitment.