Under the FIDIC Conditions of Contract, the Engineer may delegate any of the duties and powers vested in him to the Engineer’s Representative. Nevertheless, some of the delegated duties and powers might require prior approval from the Employer. The “Delegation of Authority by the Engineer” letter should identify the normally delegated clauses which deal with duties or powers of a more routine nature or which have little contractual or financial significance as well as the clauses containing powers or duties which the Engineer may or may not choose to delegate. Any such delegation or revocation shall be in writing and shall not take effect until a copy thereof been delivered to the Employer and the Contractor.

Using Project Management Information Systems (PMIS) like PMWeb help in automating the process for issuing the Delegation of Authority by the Engineer letter. PMWeb form builder module will be used to capture the fields needed for the letter such as the Resident Engineer name and title, effective date of the delegation, letter issuance date among others.

PMWeb 7 Asset Managment Forms Sub-Clause 3.2 Template

In addition, the form will include a table that will list all duties and powers that might be delegated by the Engineer. The table will list the FIDIC contract sub-clauses reference, sub-clauses title and whether the duties and powers that are part of this sub-clause will be delegated or not. As an option, the table could also include a field to verify if this was approved by Employer or not.

PMWeb 7 List of Duties and Authorities

The attachment tab will be used to keep a copy of the formal Delegation of Authority by the Engineer letter that has been issued to the Employer and Contractor. Of course, the attachment tab could include other documents such the Resident Engineer CV and other details.

PMWeb 7 Asset Managment Forms Sub-Clause 3.2 Template

The workflow tab will capture the review, approval and final approval steps before the Delegation of Authority by the Engineer letter is formally issued to the Contractor. The workflow steps could also include the Employer who needs to approve the delegation before it is formally communicated to the Contractor.

PMWeb 7 Workflow

The formal communication template of the Delegation of Authority by the Engineer letter will be created in PMWeb using PMWeb Word module. The letter will capture the fields from the Delegation of Authority by the Engineer form which will also include the table for delegated and not delegated FIDIC contract clauses.

PMWeb 7 Asset Managment Forms Sub-Clause 3.2 Template